| Chauthe Health Post Construction |
|
| 23 Aug 20 |
Project closed by the ANMF Board. |
| 28 Jun 20 |
The handover has been completed. The local government of Chauthe has given us the letter of handover and they will operate the health center as soon as possible. |
| 27 May 20 |
Letter received from Kakani Ward number 3, Chauthe about the handover of the Chauthe Community health center and they will start to operate as soon as possible. The final 5% retention will be paid to the vendor for this project. |
| 16 Mar 20 |
Status report from ANMF/Nepal: “Retaining wall is needed to secure as stated by Julia and fred from their earlier visit. We will conduct a handover ceremony soon as to hand it over to the local government over there.” |
| 10 Nov 19 |
Communication from ANMF/Nepal. |
| 8 Nov 19 |
Update from ANMF/Nepal. |
| 3 Nov 19 |
Report on 24 October site visit by ANMF/America Board member Julia Shepardson. |
| 24 Oct 19 |
ANMF/America Board member Julia Shepardson visits the Chauthe site. |
| 16 Aug 19 |
ANMF/Nepal reports: The structure of Chauthe community has almost been completed and has a week of work left. We will move forward with the final payment as soon as the structure has been completed. Few concerns are there in health center as it is in need of a retention wall as you can see on the attached photos. As we can assess this situation and come up with a solution. The Local ward office They will sustain the health center and If possible, in with support of the ward office of we can construct a retention wall which will be a huge help. |
| 1 Apr 19 |
Chauthe Health Center is in its initial stage of construction. |
| 8 Jan 19 |
ANMF/Nepal has visited Chauthe, Nuwakot to see the site in which Chauthe health center is going to be built. Dr.Subhash Acharya (president ANMF/Nepal) inspected the site which was shown to us by a local villager of Chauthe, Nuwakot, Mr.Pralab. |
| 23 Dec 18 |
Acknowledgement of funds transferred received. |
| 19 Dec 18 |
$44,600 transfered to ANMF/Nepal for Chauthe Health Post. |
| 12 Dec 18 |
Memorandum of Understanding (1, 2) signed. |
| 11 Oct 18 |
Project Approval received from Social Welfare Council (1, 2). |
| 13 Mar 18 |
Report from ANMF/Nepal: We went to submit the request for approval of the project (Chahuthe Community health care center) at Social Welfare Welfare Council (SWC) today and the official at SWC asked us to get further documents including drawing of the land where the health care center is about to be constructed, Bills of Quantities (BOQ) regarding the materials that will be used for the construction of the health care center, as well as an approval from District Health Office and an approval of the map (drawing) from the municipality. |
| 7 Mar 18 |
Fund Assurance Letter sent to ANMF/Nepal. |
| 5 Feb 18 |
The Kali Devi Agriculture Cooperative institution (Mr. Posh Nath Dhungana along with other local peoples at Chauthe) has requested ANMF/Nepal to construct a community health care center as they were not allowed to register themselves as an institution to work in the health sector. ANMF/Nepal has received letters for the construction of Chauthe community health care center from rural municipality and ward level. |
| 15 Nov 17 |
The proposal to construct a health post at Chauthe, Nuwakot was initially submitted by Kali Devi Agriculture Cooperative Limited. ANMF/Nepal requested Mr. Poush Nath Dhungana to amend their (Kali Devi Agriculture Cooperative Limited) constitution so that they can work on health sectors too. |
| 7 Aug 17 |
ANMF/Nepal is awaiting the approval from District coordination committee and/or District health office of Nuwakot district. |
| 16 Apr 17 |
Project approved by ANMF Board. ANMF Nepal has approved this project after doing their due diligence. Community co-operative that has been formed by the locals have set up funds to staff and have deposited NRS 200,000 at a local bank. Of the total cost to construct this CHC, USD $35,000 will come from funds collected by Dr Sanjaya Khanal and team. This project will be run by ANMF/Nepal in conjunction with rest of the other health facilities being constructed and monitored. |
| 10 Apr 17 |
Proposal from Kali Devi Agriculture Cooperative Limited received from ANMF/Nepal. |