Health Post – Thulosirubari
| Thulosirubari Health Post Construction | |
|---|---|
| Location: | Thulosirubari, Sindhupalchowk |
| Institution: | Nepal Ministry of Health and Population, Government of Nepal |
| Project: | ANMF has formed a special relationship with the Nepal Ministry of Health and Population to rebuild eleven health posts in rural Nepal damaged by the 2015 earthquake.
On 25th April 2015, A devastating magnitude 7.8 earthquake struck Nepal. On 12th May 2015, a large aftershock with a magnitude of 7.3 incurred more losses of lives and infrastructure. Fourteen districts were hardest hit by the earthquake namely – Sindhupalchowk, Nuwakot, Dhading, Gorkha, Rasuwa, Kavre, Bhaktapur, Lalitpur, Dolakha, Makwanpur, Ramechhap, Okhaldhunga, Sindhuli and Lamjung. Due to this devastating earthquake more than 8600 people lost their lives and 16,808 were injured. More than 2000 major surgeries were performed. A total of 408 health posts (HP), 10 primary health care centers(PHCC), 8 hospitals, 27 Ayurveda ausadhalaya/centre were completely damaged. In addition, 565 HPs, 62 PHCC, 33 hospitals, and 26 Ayurveda Centers were partially damaged. These events have created an interruption in health service delivery which may reverse the achievements that we made in the past. Additionally, there is high risk of disease outbreak in absence of immediate and adequate preparedness. Ministry of Health and Population (MoHP) endorsed the post earthquake "Health sector recovery plan" to strengthen the health service delivery in this state of emergency where America Nepal Medical Foundation sprang into action by signing a memorandum of understanding (MOU) with the MoHP on 23rd June, 2015. We were amongst the first Non governmental Organization (NGO) to sign an MOU with the Government. ANMF team proposed to build 11 Prefab health posts in partnership with the Government of Nepal and local people in the earthquake affected district of Sindhupalchowk, Nepal. The purpose of this partnership is to resume a robust and resilient health system at the affected areas in short period of time and regain confidence of public and health workforce at large. Irkhu has been added as a twelfth health post. Duipipal has been added as a thirteenth health post. |
![]() |
|
| Institution: | Nepal Ministry of Health and Population, Government of Nepal |
| Location: | Kathmandu |
![]() |
|
| Title: | Health Post Construction |
| ID: | 15MOHP001n |
| Type: | Funded Project |
| Date: | 26 June 2015 |
| Grant: | $500,000 |
| Funded: | $500,000 |
| Nepal Manager: | Dr Bhagawan Koirala |
| USA Manager: | Dr Sunil Sharma, Dr Bijay Acharya |
| Details: | ANMF has formed a special relationship with the Nepal Ministry of Health and Population to rebuild eleven health posts in rural Nepal damaged by the 2015 earthquake. The Thulosirubari health post is a Type 2 Health Post (11.3m x 7.9m x 2.7m). Irkhu has been added as a twelfth health post. Duipipal, Nuwakot has been added as a thirteenth health post. |
| Thulosirubari Health Post Construction | |
|---|---|
| 6 Apr 18 | Upon request from ANMF/Nepal, Fix it Engineering Pvt. Ltd. has checked the solar problems at 12 health posts and repaired the problems at Haibung health post and Attarpur health post. The contract between ANMF/Nepal and Fix it Eng. Pvt. Ltd. has already expired. Fix it Eng. Pvt. Ltd collected a letter from health posts where the problems were fixed. Detailed reports received for Haibung, Petku and Thulosirubari health posts. |
| 27 May 15 | Approved by Projects Committee. |
| 31 May 15 | Approved by Earthquake Emergency Committee. |
| 17 Jun 15 | $100,000 sent to ANMF/Nepal for 15MOHP001 (11 health posts). |
| 2 Jul 15 | Memorandum of understanding signed with Ministry of Health and Population (page 1, 2, 3, 4). |
| 5 Jul 15 | Contract (page 1, 2, 3) signed with Fix It Engineering Pvt. Ltd. to build eleven health posts. |
| 12 Jul 15 | Approved by ANMF/USA Board. |
| 27 Jul 15 | $200,000 sent to ANMF/Nepal for 15MOHP001 (11 health posts). |
| 1 Oct 15 | Report received. Thulosirubari health post construction is projected to commence second week of October due to delayed demolition of existing healthpost building by UNDP. |
| 9 Jan 16 | Report received. Foundation work and civil work have been completed. Truss work has already been initiated. This site was started late because of delay in demolition of existing building. It was further delayed due to ongoing economic blockade and fuel crisis. |
| 5 Feb 16 | Report received. Due to long run economic embargo creating shortage of fuel and construction materials, the project could not be carried out as planned. After long halt in construction process work has been restarted.
Thulosirubari health post Foundation work and civil work has been completed. Truss work has also been completed along with the wall installation work initiated. This site was started late because of delay in demolition of existing building. |
| 15 Mar 16 | $150,000 sent to ANMF/Nepal for 15MOHP001 (11 health posts). |
| 14 Apr 16 | Report received. Most of the work has been completed. Wall installation, ceiling work are completed. Sanitary work and electricity work are near to completion. Finishing and site clearance work are being carried out. |
| 21 Jun 16 | Report received. Construction is complete and handover yet to be done. |
| 2 Jul 16 | Health post handed over to Nepal government. |
| 21 Jul 16 | Report received regarding health posts handover ceremony. |
| 31 Jul 16 | Expense report received. |
| 7 Aug 16 | ANMF accounting for health post project. |
| 2 Oct 16 | Update on health posts. |
| 11 Dec 16 | ANMF/USA has set aside an additional $50,000 for maintaining and strengthening ANMF rebuilt health posts in response to report from ANMF/Nepal. |
| 27 Jan 17 | Report received from ANMF/Nepal. This health post has smaller boundary area compared to other health posts. The local villagers are requesting to help build a water supply system. |
| 8 Feb 18 | Letter provided by Ministry of Health regarding the handover of the prefabricated health posts across Sindhupalchowk district. |
| Thulosirubari Health Post Construction | |
|---|---|