| Medical Oxygen Generation Plant |
| |
| 26 Oct 21 |
Final Report received from ANMF/Nepal. |
| 24 Oct 21 |
Project closed by the ANMF/USA Board of Directors. |
| 24 Oct 21 |
ANMF/Nepal reports project is completed. Final report will be sent soon. |
| 5 Sep 21 |
Amit Chaudhary (Biomedical Engineer) and Bikrant Rana (ANMF/Nepal) visited Koshi Hospital on 2nd and 3rd September 2021 for the final engineer assessment of the oxygen plant. Everything seems to be in order. As the process was completed, ANMF/Nepal has handed over the oxygen plant to Koshi Hospital. A program will be conducted soon to officially hand over the Oxygen plant. (See Photos) |
| 27 Jul 21 |
Oxygen plant in operation (see Photos and Videos). |
| 7 Jul 21 |
Oxygen plant in progress (see Photos). |
| 27 Apr 21 |
Oxygen plant arriving though shipment delayed due to Suez canal crisis. |
| 2 Mar 21 |
Update received from ANMF/Nepal. “The building construction of Koshi oxygen plant has been completed and the installation of the pipeline has been discussed as per our recent visit to the site. Me along with our biomedical engineer Amit Chaudhary and the vendor visited the site and had a meeting with the authorities of Koshi Hospital and finalized where the Gas pipelines and the manifolds would be placed. The vendor has said in a month's time the plant will arrive and will be installed so after that we will hand over the Oxygen plant to Koshi Hospital.” |
| 17 Jan 21 |
The structure for the oxygen plant has almost finished and our biomedical engineer Amit Chaudhary and Office Manager Bikrant will visit the site before the installation of pipelines to make sure everything is on track. The vendor has said it will be complete in a month time. |
| 12 Dec 20 |
Tender process has finished and we have selected the vendor to procure the oxygen plant. Diagnochem International is the vendor that we had selected after being the lowest and eligible bidder for the oxygen plant on the date October 19, 2020. Diagnochem International has submitted the design for the foundation works. Diagnochem International has informed us it will take approximately 1 or 1 and half months for the oxygen plant to arrive after which we will handover it over to the Koshi Hospital, Biratnagar. |
| 1 Nov 20 |
$101,000 transferred to ANMF/Nepal. |
| 10 Jul 20 |
Technical Specification and Tender documents has been made with the help of Amit Chaudhary (Biomedical Engineer). Tender process to be carried out to procure the Oxygen plant as soon as the Corona situation will be stable. Funds are yet to be transferred. |
| 19 Mar 20 |
Memorandum of Understanding (MOU) received from ANMF/Nepal. |
| 16 Mar 20 |
Status report from ANMF/Nepal: “MOU has not been sent by ANMF-US which is to be done with ANMF-Nepal. Technical Specification and Tender documents has been made with the help of Amit Chaudhary (Biomedical Engineer). Funds are yet to be transferred.” |
| 23 Feb 20 |
Social Welfare Council (SWC) approval (1, 2) received from ANMF/Nepal. |
| 16 Feb 20 |
ANMF/Nepal Memorandum of Understanding (MOU) (1, 2) received from ANMF/Nepal. |
| 16 Feb 20 |
Communication received from ANMF/Nepal. |
| 2 Nov 19 |
Fund Assurance Letter sent to ANMF/Nepal. |
| 19 Oct 19 |
Project approved by the ANMF/America Board by web ballot. |
| 13 Oct 19 |
ANMF Projects Committee recommended that the Board approve the project. |
| 23 Sep 19 |
Novair/Oxyplus VisiO2 Oxygen Generator Monitoring & Management Brochure received from Koshi Hospital. |
| 23 Sep 19 |
Novair/Oxyplus Medical Oxygen Generators Brochure received from Koshi Hospital. |
| 23 Sep 19 |
Novair/Oxyplus Oxygen Generators Orlane SA Brochure received from Koshi Hospital. |
| 23 Sep 19 |
Novair Feed Air Units Brochure received from Koshi Hospital. |
| 23 Sep 19 |
Proposal received from Koshi Hospital. |
| 23 Sep 19 |
Grant Application received from Koshi Hospital. |